The assembly of the column steel construction supporting the cable roof of the National Stadium in Warsaw began today. This is a totally new stage in the construction work! The steel and cable roof of the Stadium consists of 12 thousand tons of steel and over 2 thousand tons of steel cables.
The Italian Cimolai company has already delivered 6,400 tons of steel construction elements to the Stadium building site. Due to their size and weight, it was a very complicated logistic operation to deliver the elements by train from Italy to Warsaw Praga goods railway station and then with vehicles to the construction site. 72 columns, each 30 meters long and weighing approx. 40 tons, with 72 parts of the ring assembled between them, each weighing over 48 tons, had to be transported through Warsaw streets at night and with traffic regulated on the route.
Stages in column installation:
![]() |
![]() |
![]() |
![]() |
Stage I

Stage II

Stage III Installing columns in spot footings

Stage IV Installing the stay cables of the steel columns for the Stadium reinforced concrete construction
Columns and ring parts will be installed using two heavy caterpillar lattice cranes with a carry weight of 600 tons. The installation will begin in the south-eastern and north-eastern part of the Stadium.The direct contractor is Mostostal Zabrze, a member of the consortium assembling the Stadium roof. Other members of the consortium are Italian Cimolai, construction manufacturer and consortium leader, and German Hightex, deliverer and installer of the membrane covering the roof above the stands.