The process of installing escalators has begun at the construction site of the National Stadium in Warsaw. The first of 34 moving stairways has already been installed. The same with 10 out of 39 elevators. Installation of 14 others is still underway.

The steel construction, units of angle-braces and guy-wires, and the cable roof construction elements are being assembled as scheduled. 20 out of 72 units have already been installed.
Installation of the aluminum and glass elevation of rooms located under the stands still continues. Approx. 30% of the 2 ha large area of external walls has already been built.